Louisiana Avenue

Louisiana Avenue Information

Louisiana Avenue Extension Phase IIC

  • Status: Under Construction
  • Limits: E. Pont Des Mouton Road to Maryview Farm Road
  • Total Cost: $11,500,000
  • Construction Start Date: September 21, 2006
  • Scope of Work: Construction of a 4-lane concrete boulevard roadway with subsurface drainage, sidewalks and street lighting.
  • Completion: Fall, 2009 

Louisiana Avenue Extension Phase II-D

  • Status: Engineering 90% Complete
  • Limits: Maryview Farm Road to Gloria Switch Road
  • Total Cost: $14,686,000
  • Anticipated Start of Construction: Spring, 2010
  • Scope of Work: Construction of a 4-lane concrete boulevard roadway with subsurface drainage, sidewalks and street lighting.

Approximate Cost of Completed Louisiana Avenue/I-10 Interchange (By LA-DOTD):  $24,600,000

TOTAL FOR LOUISIANA AVENUE (LCG & STATE): $60,000,000