Louisiana Avenue Extension Phase II-D-1
- Status: Under Construction
- Limits: Maryview Farm Road to Butcher Switch Road
- Total Cost: $7,500,000
- Anticipated Completion: Late 2012
- Scope of Work: Construction of a 4-lane concrete boulevard roadway with subsurface drainage, sidewalks and street lighting.
Louisiana Avenue Extension Phase II-D-2
- Status: Engineering 80% Complete
- Limits: Butcher Switch Road to Gloria Switch Road, with round-about at Gloria Switch Road
- Total Cost: $5,600,000
- Anticipated Start of Construction: Late, 2012
- Scope of Work: Construction of a 4-lane concrete boulevard roadway with subsurface drainage, sidewalks, street lights and a round-about at Gloria Switch Rd.
Approximate Cost of Completed Louisiana Avenue/I-10 Interchange (By LA-DOTD): $24,600,000
TOTAL FOR LOUISIANA AVENUE (LCG & STATE): $60,000,000 (Includes roadway from Willow St. to Gloria Switch Rd.)
|